6 July 2018 GMT M1 subsystem: status, design and testing
Author Affiliations +
Abstract
This paper describes the design, status, and test program for the Giant Magellan Telescope (GMT) Primary Mirror Subsystem (M1). It consists of the mirror cells, positioning system, support systems, and thermal control system. The seven 8.4m mirror segments are excluded from this paper because they are considered a separate subsystem of the M1 System.

The M1 Subsystem leverages heritage design of similar telescope systems; for example, the Magellan telescopes and the Large Binocular Telescope. The M1 Subsystem incorporates pneumatic force actuators, hardpoints, and a thermal control ventilation system.

Design developments have been introduced to address the challenging levels of performance and unique requirements needed by the GMT telescope. Imaging goals necessitate an increase in mirror support performance, figure control, and higher-levels of thermal control. Additionally, there are challenges associated with matching and tracking the relative position of the seven mirror segments for mirror phasing. The design of the static support system needs to protect the mirrors from loads transmitted through the structure during an earthquake. Finally, the telescope design with interchangeable off-axis mirror cells necessitate mirror cells and support components that function under any range of gravitational vector orientations

. A full-scale Test Cell prototype is being constructed including production versions of mirror cell components to test and validate the M1 subsystem design. A Mirror Simulator will be used with the Test Cell to validate the M1 Control System. Later, a primary mirror segment will be used with the Test Cell to perform optical tests at the University of Arizona.
© (2018) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Francisco Aguayo, Dave Ashby, Erich Bugueno, Barbara Fischer, John Ford, Peter Gray, Michael Gusick, Anthony Hebert, Zaven Kechichian, Trupti Ranka, Dev Sharma, Jose Soto, Hector Swett, Divya Thanasekaran, Frank Tian, and Abhijit Wadhavkar "GMT M1 subsystem: status, design and testing", Proc. SPIE 10700, Ground-based and Airborne Telescopes VII, 1070036 (6 July 2018); https://doi.org/10.1117/12.2312937
Lens.org Logo
CITATIONS
Cited by 1 scholarly publication.
Advertisement
Advertisement
RIGHTS & PERMISSIONS
Get copyright permission  Get copyright permission on Copyright Marketplace
KEYWORDS
Mirrors

Actuators

Control systems

Fluctuations and noise

Telescopes

Interfaces

Sensors

RELATED CONTENT

Development of a test rig for the active control of...
Proceedings of SPIE (March 21 1997)
PAMELA phase I testing and verification on a 0.5...
Proceedings of SPIE (April 26 1995)
Adaptive secondary mirror for the 6.5 m conversion of the...
Proceedings of SPIE (September 27 1999)
E-ELT M1 test facility
Proceedings of SPIE (September 17 2012)

Back to Top