12 July 2008 Commissioning and early operations of the Large Binocular Telescope
Author Affiliations +
Abstract
By June 2008, The Large Binocular Telescope Observatory will have supported two full semesters of observing with prime focus imaging. Interspersed were optical alignment and initiation of binocular mode for the prime focus, as well as installation and initial commissioning of the first bent Gregorian focal station. We examine the lost time statistics and distribution of issues that reduced on-sky access in the context of the limited technical support provided for observing. We also note some of the restrictions imposed by the alternation of engineering and commissioning activities with scheduled observing time. The goal is to apply the lessons learned to the continuing period of observation plus commissioning anticipated as new spectroscopic, adaptive optics, and interferometric capabilities are added through 2010.
© (2008) COPYRIGHT Society of Photo-Optical Instrumentation Engineers (SPIE). Downloading of the abstract is permitted for personal use only.
Richard F. Green, Richard F. Green, John M. Hill, John M. Hill, James H. Slagle, James H. Slagle, Joar Brynnel, Joar Brynnel, Norman J. Cushing, Norman J. Cushing, R. Mark Wagner, R. Mark Wagner, Marco Pedani, Marco Pedani, David Thompson, David Thompson, } "Commissioning and early operations of the Large Binocular Telescope", Proc. SPIE 7016, Observatory Operations: Strategies, Processes, and Systems II, 70160A (12 July 2008); doi: 10.1117/12.790137; https://doi.org/10.1117/12.790137
PROCEEDINGS
10 PAGES


SHARE
RELATED CONTENT

The new MMT
Proceedings of SPIE (September 27 2004)
Status and perspective of Subaru Telescope Project
Proceedings of SPIE (March 20 1997)
On sky results of the adaptive optics MACAO for the...
Proceedings of SPIE (June 26 2006)
Operations model for the Large Binocular Telescope
Proceedings of SPIE (June 28 2006)

Back to Top