1 December 1977 Development of Solar Tower Program in the United States
Author Affiliations +
Abstract
With strong governmental support and broad-based public approval, the United States solar energy program has expanded rapidly in the last few years. In particular, we have traced the history and development of the solar tower from an idea in 1969 through first federal funding in 1973, to a program to initiate pilot plant construction in 1977. About 3,000 heliostats will reflect sunlight onto a central receiver in which 500°C steam will be generated to drive a turbo-generator. With this 10 MWe plant scheduled to feed electricity into a utility grid in 1980, a 50-100 MWe demonstration plant is proposed to be on line in 1985.
Lorin L. Vant-Hull, "Development of Solar Tower Program in the United States," Optical Engineering 16(6), 166575 (1 December 1977). https://doi.org/10.1117/12.7972164 . Submission:
JOURNAL ARTICLE
5 PAGES


SHARE
RELATED CONTENT